1. The motor of the grinder must be reliably grounded during work to avoid unnecessary accidents.

2. The grinder should be started under no load, and then run dry for 2 to 3 minutes, and then feed the material after observing that the machine has no abnormal conditions. When feeding, try to feed evenly and ensure that the motor is working under rated load. Observe that the bearing temperature should not be too high at any time. If there is overheating, it should be shut down immediately for inspection to avoid damage to the bearing, spindle, etc.

3. After feeding, let the grinder continue to run for 1 to 2 minutes, and then stop the machine after all the materials in the standby are crushed and discharged.

4. When cleaning the blockage in the crushing chamber, adjusting and replacing the hammers, screens and belts, the power must be cut off, and the machine can be stopped after the machine stops running to ensure safety.

5. Regularly check the hammer and flat teeth for cracks and wear. Regularly refuel the bearings.

6. In order to avoid dust explosion, the crushing work site should be spacious, ventilated, and equipped with reliable fire prevention facilities.

The above are the precautions during the operation of the raw coal crusher in the briquette equipment production line. It is hoped that the operators in the briquette equipment production line will perform operations in strict accordance with the work requirements to ensure the normal production of the raw coal crusher.